1
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network
The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :
The standard deviation of the critical path is
2
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network
The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :
The critical path duration of the network (in days) is
3
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
For the network below, the objective is to find the length of the shortest path from node $$P$$ to node $$G.$$ Let $${d_{ij}}$$ be the length of directed are from node $$i$$ to node $$j$$. Let $${s_j}$$ be the length of the shortest path from $$P$$ to node $$j.$$ Which of the following equations can be used to find $${s_G}$$?
4
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$)
The standard deviation of the critical path of the project is
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery