1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The project activities, precedence relationships and durations are described in the table. The critical path of the project is
2
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network
The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :
The critical path duration of the network (in days) is
3
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network
The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :
The standard deviation of the critical path is
4
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
For the network below, the objective is to find the length of the shortest path from node $$P$$ to node $$G.$$ Let $${d_{ij}}$$ be the length of directed are from node $$i$$ to node $$j$$. Let $${s_j}$$ be the length of the shortest path from $$P$$ to node $$j.$$ Which of the following equations can be used to find $${s_G}$$?
Questions Asked from Pert and Cpm (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME 2022 Set 2 (1)
GATE ME 2022 Set 1 (1)
GATE ME 2017 Set 2 (1)
GATE ME 2016 Set 2 (1)
GATE ME 2015 Set 2 (1)
GATE ME 2015 Set 1 (1)
GATE ME 2014 Set 4 (1)
GATE ME 2014 Set 2 (1)
GATE ME 2014 Set 3 (1)
GATE ME 2012 (2)
GATE ME 2010 (1)
GATE ME 2009 (2)
GATE ME 2008 (1)
GATE ME 2006 (2)
GATE ME 2005 (1)
GATE ME 2003 (1)
GATE ME 2002 (1)
GATE ME 1990 (1)
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude