1
GATE ME 2015 Set 2
Numerical
+2
-0
A project consists of $$7$$ activities. The network along with the time durations (in days) for various activities is shown in the figure. GATE ME 2015 Set 2 Industrial Engineering - Pert and Cpm Question 11 English

The minimum time (in days) for completion of the project is _____________

Your input ____
2
GATE ME 2014 Set 4
MCQ (Single Correct Answer)
+2
-0.6
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities $$e$$ and $$f,$$ respectively, are GATE ME 2014 Set 4 Industrial Engineering - Pert and Cpm Question 13 English
A
$$0$$ and $$4$$
B
$$1$$ and $$4$$
C
$$2$$ and $$3$$
D
$$3$$ and $$1$$
3
GATE ME 2014 Set 2
Numerical
+2
-0
A project has four activities $$P,Q, R$$ and $$S$$ as shown below. GATE ME 2014 Set 2 Industrial Engineering - Pert and Cpm Question 15 English

The normal cost of the project is Rs. $$10,000/-$$ and the overhead cost is Rs. $$200/-$$ per day. If the project duration has to be crashed down to $$9$$ days, the total cost (in Rupees) of the project is ______________.

Your input ____
4
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+2
-0.6
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity $$4$$-$$6$$ and the project duration, respectively, are GATE ME 2014 Set 3 Industrial Engineering - Pert and Cpm Question 14 English
A
$$2, 13$$
B
$$0, 13$$
C
$$-2, 13$$
D
$$2, 12$$