1
GATE ME 2015 Set 2
Numerical
+2
-0
A project consists of $$7$$ activities. The network along with the time durations (in days) for various activities is shown in the figure. GATE ME 2015 Set 2 Industrial Engineering - Pert and Cpm Question 10 English

The minimum time (in days) for completion of the project is _____________

Your input ____
2
GATE ME 2015 Set 1
MCQ (Single Correct Answer)
+2
-0.6
Following data refers to the activities of a project, where, node $$1$$ refers to the start and node $$5$$ refers to the end of the project. GATE ME 2015 Set 1 Industrial Engineering - Pert and Cpm Question 11 English

The critical path $$(CP)$$ in the network is

A
$$1-2-3-5$$
B
$$1-4-3-5$$
C
$$1-2-3-4-5$$
D
$$1-4-5$$
3
GATE ME 2014 Set 2
Numerical
+2
-0
A project has four activities $$P,Q, R$$ and $$S$$ as shown below. GATE ME 2014 Set 2 Industrial Engineering - Pert and Cpm Question 14 English

The normal cost of the project is Rs. $$10,000/-$$ and the overhead cost is Rs. $$200/-$$ per day. If the project duration has to be crashed down to $$9$$ days, the total cost (in Rupees) of the project is ______________.

Your input ____
4
GATE ME 2014 Set 4
MCQ (Single Correct Answer)
+2
-0.6
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities $$e$$ and $$f,$$ respectively, are GATE ME 2014 Set 4 Industrial Engineering - Pert and Cpm Question 12 English
A
$$0$$ and $$4$$
B
$$1$$ and $$4$$
C
$$2$$ and $$3$$
D
$$3$$ and $$1$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12