1
GATE ME 2025
Numerical
+2
-0

A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is __________hours (answer in integer).

$$ \begin{array}{|c|c|c|} \hline \text { Activity } & \text { Immediate predecessor } & \text { Duration(hours) } \\ \hline A & - & 4 \\ \hline B & A & 8 \\ \hline C & A & 5 \\ \hline D & B & 2 \\ \hline E & B & 7 \\ \hline F & C & 6 \\ \hline G & D & 3 \\ \hline H & E, F, G & 9 \\ \hline \end{array} $$
Your input ____
2
GATE ME 2022 Set 2
Numerical
+2
-0

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is ______ weeks (in integer).

Activity

Time estimates (in weeks)

Immediate predecessor(s)

Optimistic time

Most likely time

Pessimistic time

A

4

5

6

None

B

1

3

5

A

C

1

2

3

A

D

2

4

6

C

E

3

4

5

B, D

Your input ____
3
GATE ME 2022 Set 1
MCQ (Single Correct Answer)
+2
-0.66

Activities A to K are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is to be completed in the minimum possible time, the latest finish time for the activity G is ______ hours.

$$ \begin{array}{|c|c|c|} \hline \text { Activity } & \text { Time (hours) } & \text { Immediate predecessors } \\ \hline \text { A } & 2 & - \\ \hline \text { B } & 3 & - \\ \hline \text { C } & 2 & - \\ \hline \text { D } & 4 & \text { A } \\ \hline \text { E } & 5 & \text { B } \\ \hline \text { F } & 4 & \text { B } \\ \hline \text { G } & 3 & \text { C } \\ \hline \text { H } & 10 & \text { D, E } \\ \hline \text { I } & 5 & \text { F } \\ \hline \text { J } & 8 & \text { G } \\ \hline \text { K } & 3 & \text { H, I, J } \\ \hline \end{array} $$
A
5
B
10
C
8
D
9
4
GATE ME 2017 Set 2
Numerical
+2
-0
A project starts with activity $$A$$ and ends with activity $$F.$$ The precedence relation and durations of the activities are as per the following table: GATE ME 2017 Set 2 Industrial Engineering - Pert and Cpm Question 9 English

The minimum project completion time (in days) is ___________

Your input ____
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering