1
GATE ME 1998
Subjective
+5
-0
A job shop has $$6$$ orders to be completed by a single turning center. The processing times and due dates are as follows: GATE ME 1998 Industrial Engineering - Scheduling Question 3 English

Assume that all orders are ready for processing. Give a production schedule that minimizes the average flow time. Compare this schedule with one that minimizes tardiness (lateness).

2
GATE ME 1996
Subjective
+5
-0
A job shop incurs a cost of Rs.$$60$$/- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with the following data: GATE ME 1996 Industrial Engineering - Scheduling Question 4 English

Which schedule will minimize the total cost?
What is the minimum total cost?
Which jobs (if any) fail to meet their due dates?

3
GATE ME 1990
Subjective
+5
-0
Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below GATE ME 1990 Industrial Engineering - Scheduling Question 5 English

Considering mean lateness and mean flow time, evaluate the shortest-time rule and least-slack rule and recommend the desirable rule.

GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12