1
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+2
-0.6
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity $$4$$-$$6$$ and the project duration, respectively, are
2
GATE ME 2014 Set 4
MCQ (Single Correct Answer)
+2
-0.6
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities $$e$$ and $$f,$$ respectively, are
3
GATE ME 2014 Set 2
Numerical
+2
-0
A project has four activities $$P,Q, R$$ and $$S$$ as shown below.
The normal cost of the project is Rs. $$10,000/-$$ and the overhead cost is Rs. $$200/-$$ per day. If the project duration has to be crashed down to $$9$$ days, the total cost (in Rupees) of the project is ______________.
Your input ____
4
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
If the duration of activity $$''f ''$$ alone is changed from $$9$$ to $$10$$ days, then the
GATE ME Subjects
Browse all chapters by subject
Theory of Machines
Engineering Mechanics
Production Engineering
Strength of Materials
Turbo Machinery
Engineering Mathematics
Machine Design
Heat Transfer
Industrial Engineering
Thermodynamics
General Aptitude