1
GATE ME 2014 Set 4
MCQ (Single Correct Answer)
+2
-0.6
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities $$e$$ and $$f,$$ respectively, are GATE ME 2014 Set 4 Industrial Engineering - Pert and Cpm Question 10 English
A
$$0$$ and $$4$$
B
$$1$$ and $$4$$
C
$$2$$ and $$3$$
D
$$3$$ and $$1$$
2
GATE ME 2014 Set 2
Numerical
+2
-0
A project has four activities $$P,Q, R$$ and $$S$$ as shown below. GATE ME 2014 Set 2 Industrial Engineering - Pert and Cpm Question 12 English

The normal cost of the project is Rs. $$10,000/-$$ and the overhead cost is Rs. $$200/-$$ per day. If the project duration has to be crashed down to $$9$$ days, the total cost (in Rupees) of the project is ______________.

Your input ____
3
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+2
-0.6
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity $$4$$-$$6$$ and the project duration, respectively, are GATE ME 2014 Set 3 Industrial Engineering - Pert and Cpm Question 11 English
A
$$2, 13$$
B
$$0, 13$$
C
$$-2, 13$$
D
$$2, 12$$
4
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below. GATE ME 2012 Industrial Engineering - Pert and Cpm Question 14 English

The critical path for the project is

A
$$a-b-e-g-h$$
B
$$a-c-g-h$$
C
$$a-d-f-h$$
D
$$a-b-c-f-h$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Joint Entrance Examination
JEE MainJEE AdvancedWB JEEBITSATMHT CET
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN