Production Planning and Control · Industrial Engineering · GATE ME

Start Practice

Marks 1

Marks 2

1

A solid part (see figure) of polymer material is to be fabricated by additive manufacturing (AM) in square-shaped layers starting from the bottom of the part working upwards. The nozzle diameter of the AM machine is a/10 mm and the nozzle follows a linear serpentine path parallel to the sides of the square layers with a feed rate of a/5 mm/min.

Ignore any tool path motions other than those involved in adding material, and any other delays between layers or the serpentine scan lines.

The time taken to fabricate this part is ___________ minutes.

(Answer in integer)

GATE ME 2023 Industrial Engineering - Production Planning and Control Question 1 English

GATE ME 2023
2

The product structure diagram shows the number of different components required at each level to produce one unit of the final product P. If there are 50 units of on hand inventory of component A, the number of additional units of component A needed to produce 10 units of product P is _________ (in integer).

GATE ME 2022 Set 1 Industrial Engineering - Production Planning and Control Question 2 English
GATE ME 2022 Set 1
3
A manufacturer has the following data regarding a product:
Fixed cost per month $$=$$ Rs. $$50,000$$
Variable cost per unit $$=$$ Rs. $$200$$
Selling price per unit $$=$$ Rs. $$300$$
Production capacity $$=$$ $$1500$$ units per month

If the production is carried out at $$80\% $$ of the rated capacity, then the monthly profit (in Rs.) is ______________

GATE ME 2015 Set 2
4
Capacities of production of an item over $$3$$ consecutive months in regular time are $$100,$$ $$100$$ and $$80$$ and in overtime are $$20,$$ $$20$$ and $$40.$$ The demands over those $$3$$ months are $$90,$$ $$130$$ and $$110.$$ The cost of production in regular time and overtime are respectively Rs. $$20$$ per item and Rs. $$24$$ per item. Inventory carrying cost is Rs. $$2$$ per item per month. The levels of starting and final inventory are nil. Backorder is not permitted. For minimum cost of plan, the level of planned production in overtime in the third month is
GATE ME 2007
5
GATE ME 1995 Industrial Engineering - Production Planning and Control Question 6 English
GATE ME 1995

Marks 5

EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12