1
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A project has six activities $$(A$$ to $$F)$$ with respective activity durations $$7,5,6,6,8,4$$ days. The network has three paths $$A-B,C-D$$ and $$E-F.$$ All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by $$1$$ day is
2
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
A project consists of activities $$A$$ to $$M$$ shown in the net in the following figure with the duration of the activities marked in days.
The project can be completed
3
GATE ME 2002
MCQ (Single Correct Answer)
+2
-0.6
A project consists of three parallel paths with mean durations and variances of $$(10,4), (12,4)$$ and $$(12,9)$$ respectively. According to the standard $$PERT$$ assumptions, the distribution of the project duration is
4
GATE ME 1990
MCQ (Single Correct Answer)
+2
-0.6
In the construction of networks, dummy activities are introduced in order to :
Questions Asked from Pert and Cpm (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME 2022 Set 2 (1)
GATE ME 2022 Set 1 (1)
GATE ME 2017 Set 2 (1)
GATE ME 2016 Set 2 (1)
GATE ME 2015 Set 2 (1)
GATE ME 2015 Set 1 (1)
GATE ME 2014 Set 4 (1)
GATE ME 2014 Set 2 (1)
GATE ME 2014 Set 3 (1)
GATE ME 2012 (2)
GATE ME 2010 (1)
GATE ME 2009 (2)
GATE ME 2008 (1)
GATE ME 2006 (2)
GATE ME 2005 (1)
GATE ME 2003 (1)
GATE ME 2002 (1)
GATE ME 1990 (1)
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude