Scheduling · Industrial Engineering · GATE ME

Start Practice

Marks 1

GATE ME 2024
A set of jobs $U, V, W, X, Y, Z$ arrive at time $t = 0$ to a production line consisting of two workstations in series. Each job must be processed by b...

Marks 2

GATE ME 2022 Set 2
Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minim...
GATE ME 2017 Set 1
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ________...
GATE ME 2010
Four jobs are to be processed on a machine as per data listed in the table. If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, t...
GATE ME 2010
Four jobs are to be processed on a machine as per data listed in the table. Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is...
GATE ME 2009
Six jobs arrived in a sequence as given below: Average flow time (in days) for the above jobs using Shortest Processing Time rule is ...
GATE ME 2008
A set of $$5$$ jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job i...

Marks 5

GATE ME 1998
A job shop has $$6$$ orders to be completed by a single turning center. The processing times and due dates are as follows: Assume that all orders ...
GATE ME 1996
A job shop incurs a cost of Rs.$$60$$/- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with th...
GATE ME 1990
Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below Considering mean lateness ...
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12