1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
The table gives details of an assembly line.
What is the line efficiency of the assembly line?
2
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce $$80$$ units during a regular $$8$$-hour shift. This operation consists of three activities as below .
For line balancing the number of work stations required for the activities $$M, E$$ and $$T$$ would respectively be
3
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
In an assembly line for assembling toys, five workers are assigned tasks which take times of $$10, 8, 6, 9$$ and $$10$$ minutes respectively. The balance delay for the line is
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery