1
GATE ME 2017 Set 2
Numerical
+2
-0
A project starts with activity $$A$$ and ends with activity $$F.$$ The precedence relation and durations of the activities are as per the following table:
The minimum project completion time (in days) is ___________
Your input ____
2
GATE ME 2016 Set 2
Numerical
+2
-0
A project consists of $$14$$ activities, $$A$$ to $$N$$. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node $$10$$ is _____________
Your input ____
3
GATE ME 2015 Set 2
Numerical
+2
-0
A project consists of $$7$$ activities. The network along with the time durations (in days) for various activities is shown in the figure.
The minimum time (in days) for completion of the project is _____________
Your input ____
4
GATE ME 2015 Set 1
MCQ (Single Correct Answer)
+2
-0.6
Following data refers to the activities of a project, where, node $$1$$ refers to the start and node $$5$$ refers to the end of the project.
The critical path $$(CP)$$ in the network is
Questions Asked from Pert and Cpm (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME 2022 Set 2 (1)
GATE ME 2022 Set 1 (1)
GATE ME 2017 Set 2 (1)
GATE ME 2016 Set 2 (1)
GATE ME 2015 Set 2 (1)
GATE ME 2015 Set 1 (1)
GATE ME 2014 Set 4 (1)
GATE ME 2014 Set 2 (1)
GATE ME 2014 Set 3 (1)
GATE ME 2012 (2)
GATE ME 2010 (1)
GATE ME 2009 (2)
GATE ME 2008 (1)
GATE ME 2006 (2)
GATE ME 2005 (1)
GATE ME 2003 (1)
GATE ME 2002 (1)
GATE ME 1990 (1)
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude