1
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below. GATE ME 2012 Industrial Engineering - Pert and Cpm Question 13 English

If the duration of activity $$''f ''$$ alone is changed from $$9$$ to $$10$$ days, then the

A
critical path remains the same and the total duration to complete the project changes to $$19$$ days.
B
critical path and the total duration to complete the project remains the same.
C
critical path changes but the total duration to complete the project remains the same.
D
critical path changes and the total duration to complete the project changes to $$17$$ days.
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The project activities, precedence relationships and durations are described in the table. The critical path of the project is GATE ME 2010 Industrial Engineering - Pert and Cpm Question 16 English
A
$$P-R-T-V$$
B
$$Q-S-T-V$$
C
$$P-R-U-W$$
D
$$Q-S-U-W$$
3
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network GATE ME 2009 Industrial Engineering - Pert and Cpm Question 18 English 1

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :

GATE ME 2009 Industrial Engineering - Pert and Cpm Question 18 English 2

The critical path duration of the network (in days) is

A
$$11$$
B
$$14$$
C
$$17$$
D
$$18$$
4
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network GATE ME 2009 Industrial Engineering - Pert and Cpm Question 17 English 1

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :

GATE ME 2009 Industrial Engineering - Pert and Cpm Question 17 English 2

The standard deviation of the critical path is

A
$$0.33$$
B
$$0.55$$
C
$$0.77$$
D
$$1.66$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12