GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
If the duration of activity $$''f ''$$ alone is changed from $$9$$ to $$10$$ days, then the
2
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
The critical path for the project is
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The project activities, precedence relationships and durations are described in the table. The critical path of the project is
4
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network
The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :
The standard deviation of the critical path is
GATE ME Subjects
Browse all chapters by subject
Theory of Machines
Engineering Mechanics
Production Engineering
Strength of Materials
Turbo Machinery
Engineering Mathematics
Machine Design
Heat Transfer
Industrial Engineering
Thermodynamics
General Aptitude