1
GATE ME 2016 Set 2
Numerical
+2
-0
A project consists of $$14$$ activities, $$A$$ to $$N$$. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node $$10$$ is _____________ GATE ME 2016 Set 2 Industrial Engineering - Pert and Cpm Question 7 English
Your input ____
2
GATE ME 2015 Set 2
Numerical
+2
-0
A project consists of $$7$$ activities. The network along with the time durations (in days) for various activities is shown in the figure. GATE ME 2015 Set 2 Industrial Engineering - Pert and Cpm Question 8 English

The minimum time (in days) for completion of the project is _____________

Your input ____
3
GATE ME 2015 Set 1
MCQ (Single Correct Answer)
+2
-0.6
Following data refers to the activities of a project, where, node $$1$$ refers to the start and node $$5$$ refers to the end of the project. GATE ME 2015 Set 1 Industrial Engineering - Pert and Cpm Question 9 English

The critical path $$(CP)$$ in the network is

A
$$1-2-3-5$$
B
$$1-4-3-5$$
C
$$1-2-3-4-5$$
D
$$1-4-5$$
4
GATE ME 2014 Set 4
MCQ (Single Correct Answer)
+2
-0.6
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities $$e$$ and $$f,$$ respectively, are GATE ME 2014 Set 4 Industrial Engineering - Pert and Cpm Question 10 English
A
$$0$$ and $$4$$
B
$$1$$ and $$4$$
C
$$2$$ and $$3$$
D
$$3$$ and $$1$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Joint Entrance Examination
JEE MainJEE AdvancedWB JEEBITSAT
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN