Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.
|
Part |
Milling (hours) |
Polishing (hours) |
|
P1 |
8 |
6 |
|
P2 |
3 |
2 |
|
P3 |
3 |
4 |
|
P4 |
4 |
6 |
|
P5 |
5 |
7 |
|
P6 |
6 |
4 |
|
P7 |
2 |
1 |
2
GATE ME 2017 Set 1
Numerical
+2
-0
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days.
Your input ____
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.
Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.
If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery