1
GATE ME 2002
Subjective
+5
-0
The precedence relations and durations of jobs in a project are given below:
(a) Draw the activity-on-arc project network
(b) Determine all critical path(s) and their duration(s).
(c) What is the total float for jobs $$B$$ and $$D?$$
(a) Draw the activity-on-arc project network
(b) Determine all critical path(s) and their duration(s).
(c) What is the total float for jobs $$B$$ and $$D?$$
2
GATE ME 2000
Subjective
+5
-0
Given below are the data for a project network.
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
3
GATE ME 1997
Subjective
+5
-0
A project plan is given below:
(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.
4
GATE ME 1995
Subjective
+5
-0
A project with the following data is to be implemented:
(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery