1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 20 English

The expected completion time of the project is

A
$$238$$ days
B
$$224$$ days
C
$$171$$ days
D
$$155$$ days
2
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 19 English

The standard deviation of the critical path of the project is

A
$$\sqrt {151} $$ days
B
$$\sqrt {155} $$ days
C
$$\sqrt {200} $$ days
D
$$\sqrt {238} $$ days
3
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A project has six activities $$(A$$ to $$F)$$ with respective activity durations $$7,5,6,6,8,4$$ days. The network has three paths $$A-B,C-D$$ and $$E-F.$$ All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by $$1$$ day is
A
$$1$$
B
$$2$$
C
$$3$$
D
$$6$$
4
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
A project consists of activities $$A$$ to $$M$$ shown in the net in the following figure with the duration of the activities marked in days.

The project can be completed

A
between $$18,$$ $$19$$ day
B
between $$20, 22$$ days
C
between $$24, 26$$ days
D
between $$60, 70$$ days
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12