1
GATE ME 2014
MCQ (Single Correct Answer)
+1
-0.3
The total number of decision variables in the objective function of an assignment problem of size $$n\,\, \times \,\,n$$ ($$n$$ jobs and $$n$$ machines) is
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery