1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$)
The standard deviation of the critical path of the project is
2
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
A project has six activities $$(A$$ to $$F)$$ with respective activity durations $$7,5,6,6,8,4$$ days. The network has three paths $$A-B,C-D$$ and $$E-F.$$ All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by $$1$$ day is
3
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
A project consists of activities $$A$$ to $$M$$ shown in the net in the following figure with the duration of the activities marked in days.
The project can be completed
4
GATE ME 2002
MCQ (Single Correct Answer)
+2
-0.6
A project consists of three parallel paths with mean durations and variances of $$(10,4), (12,4)$$ and $$(12,9)$$ respectively. According to the standard $$PERT$$ assumptions, the distribution of the project duration is
GATE ME Subjects
Browse all chapters by subject
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude