1
GATE ME 2002
MCQ (Single Correct Answer)
+2
-0.6
A project consists of three parallel paths with mean durations and variances of $$(10,4), (12,4)$$ and $$(12,9)$$ respectively. According to the standard $$PERT$$ assumptions, the distribution of the project duration is
2
GATE ME 1990
MCQ (Single Correct Answer)
+2
-0.6
In the construction of networks, dummy activities are introduced in order to :