GATE ME 2014
The total number of decision variables in the objective function of an assignment problem of size $$n\,\, \times \,\,n$$ ($$n$$ jobs and $$n$$ machin...

Marks 2

GATE ME 2022 Set 1
An assignment problem is solved to minimize the total processing time of four jobs (1, 2, 3 and 4) on four different machines such that each job is pr...
GATE ME 2006
A firm is required to procure three items $$(P, Q$$ and $$R).$$ The prices quoted for these items (in Rs.) by suppliers $${S_1},{S_2},$$ and $${S_3}$$...