1
GATE ME 2002
Subjective
+5
-0
The precedence relations and durations of jobs in a project are given below:
(a) Draw the activity-on-arc project network
(b) Determine all critical path(s) and their duration(s).
(c) What is the total float for jobs $$B$$ and $$D?$$
(a) Draw the activity-on-arc project network
(b) Determine all critical path(s) and their duration(s).
(c) What is the total float for jobs $$B$$ and $$D?$$
2
GATE ME 2000
Subjective
+5
-0
Given below are the data for a project network.
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
3
GATE ME 1997
Subjective
+5
-0
A project plan is given below:
(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.
4
GATE ME 1995
Subjective
+5
-0
A project with the following data is to be implemented:
(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.
Questions Asked from Pert and Cpm (Marks 5)
Number in Brackets after Paper Indicates No. of Questions
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude