The precedence relations and durations of jobs in a project are given below: GATE ME 2002 Industrial Engineering - Pert and Cpm Question 1 English
(a) Draw the activity-on-arc project network
(b) Determine all critical path(s) and their duration(s).
(c) What is the total float for jobs $$B$$ and $$D?$$
2
GATE ME 2000
Subjective
+5
-0
Given below are the data for a project network. GATE ME 2000 Industrial Engineering - Pert and Cpm Question 2 English
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
3
GATE ME 1997
Subjective
+5
-0
A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 3 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

4
GATE ME 1995
Subjective
+5
-0
A project with the following data is to be implemented: GATE ME 1995 Industrial Engineering - Pert and Cpm Question 4 English

(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.