1
GATE ME 2000
Subjective
+5
-0
Given below are the data for a project network. GATE ME 2000 Industrial Engineering - Pert and Cpm Question 2 English
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
2
GATE ME 1997
Subjective
+5
-0
A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 3 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

3
GATE ME 1995
Subjective
+5
-0
A project with the following data is to be implemented: GATE ME 1995 Industrial Engineering - Pert and Cpm Question 4 English

(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.

4
GATE ME 1993
Subjective
+5
-0
For a small project with five jobs, the following data is given GATE ME 1993 Industrial Engineering - Pert and Cpm Question 5 English
(i) Draw the project network in activity on arc mode
(ii) Under $$PERT$$ assumptions, determine the distribution of project duration.
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12