1
GATE ME 2000
Subjective
+5
-0
Given below are the data for a project network. GATE ME 2000 Industrial Engineering - Pert and Cpm Question 5 English
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
2
GATE ME 1997
Subjective
+5
-0
A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 6 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

3
GATE ME 1995
Subjective
+5
-0
A project with the following data is to be implemented: GATE ME 1995 Industrial Engineering - Pert and Cpm Question 7 English

(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.

4
GATE ME 1993
Subjective
+5
-0
For a small project with five jobs, the following data is given GATE ME 1993 Industrial Engineering - Pert and Cpm Question 8 English
(i) Draw the project network in activity on arc mode
(ii) Under $$PERT$$ assumptions, determine the distribution of project duration.
GATE ME Subjects
Turbo Machinery
EXAM MAP