GATE ME 1993
Subjective
+5
-0
For a small project with five jobs, the following data is given
(i) Draw the project network in activity on arc mode
(ii) Under $$PERT$$ assumptions, determine the distribution of project duration.
(i) Draw the project network in activity on arc mode
(ii) Under $$PERT$$ assumptions, determine the distribution of project duration.
Questions Asked from Pert and Cpm (Marks 5)