1
GATE ME 2009
MCQ (Single Correct Answer)
+1
-0.3
The expected time $$\left( {{t_e}} \right)$$ of a $$PERT$$ activity in terms of optimistic time $$\left( {{t_0}} \right)$$, pessimistic $$\left( {{t_p}} \right)$$ and most likely time $$\left( {{t_L}} \right)$$ is given by
A
$${t_e} = {{{t_0} + 4{t_L} + {t_P}} \over 6}$$
B
$${t_e} = {{{t_0} + 4{t_P} + {t_L}} \over 6}$$
C
$${t_e} = {{{t_0} + 4{t_L} + {t_P}} \over 3}$$
D
$${t_e} = {{{t_0} + 4{t_P} + {t_L}} \over 3}$$
2
GATE ME 2004
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT$$ analysis a critical activity has
A
maximum Float
B
zero Float
C
maximum Cost
D
minimum Cost
3
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
A dummy activity is used in $$PERT$$ network to describe
A
Precedence relationship
B
Necessary time delay
C
Resource restriction
D
Resource idleness
4
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT,$$ the distribution of activity times is assumed to be
A
Normal
B
Gamma
C
Beta
D
Exponential
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
CBSE
Class 12