1
GATE ME 2004
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT$$ analysis a critical activity has
A
maximum Float
B
zero Float
C
maximum Cost
D
minimum Cost
2
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
A dummy activity is used in $$PERT$$ network to describe
A
Precedence relationship
B
Necessary time delay
C
Resource restriction
D
Resource idleness
3
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT,$$ the distribution of activity times is assumed to be
A
Normal
B
Gamma
C
Beta
D
Exponential