1
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT,$$ the distribution of activity times is assumed to be
Questions Asked from Pert and Cpm (Marks 1)
Number in Brackets after Paper Indicates No. of Questions
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude