1
GATE ME 2026
MCQ (Single Correct Answer)
+2
-0

Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.

$$ \begin{array}{|c|c|c|} \hline \text { Job } & \text { Due date } & \text { Work remaining (in days) } \\ \hline \text { M } & 26 & 5 \\ \hline \text { N } & 24 & 10 \\ \hline \text { O } & 28 & 10 \\ \hline \text { P } & 31 & 5 \\ \hline \end{array} $$

Which job(s) has/have critical ratio less than unity?

A

Job N and Job O

B

Job M and Job N

C

Job P

D

Job O and Job P

2
GATE ME 2022 Set 2
MCQ (Single Correct Answer)
+2
-0.66

Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.

Part

Milling (hours)

Polishing (hours)

P1

8

6

P2

3

2

P3

3

4

P4

4

6

P5

5

7

P6

6

4

P7

2

1

A
31
B
33
C
30
D
32
3
GATE ME 2017 Set 1
Numerical
+2
-0
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days. GATE ME 2017 Set 1 Industrial Engineering - Scheduling Question 7 English
Your input ____
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 9 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$

GATE ME Subjects

Browse all chapters by subject

Turbo Machinery