1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.
Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is
2
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Six jobs arrived in a sequence as given below:
Average flow time (in days) for the above jobs using Shortest Processing Time rule is
3
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A set of $$5$$ jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. $$K$$ per day.
A schedule that minimizes the total inventory cost is
Questions Asked from Scheduling (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude