1
GATE ME 2022 Set 2
MCQ (Single Correct Answer)
+2
-0.66
Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.
Part |
Milling (hours) |
Polishing (hours) |
P1 |
8 |
6 |
P2 |
3 |
2 |
P3 |
3 |
4 |
P4 |
4 |
6 |
P5 |
5 |
7 |
P6 |
6 |
4 |
P7 |
2 |
1 |
2
GATE ME 2017 Set 1
Numerical
+2
-0
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days.
Your input ____
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.
If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table.
Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is
Questions Asked from Scheduling (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude