Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.

Part

Milling (hours)

Polishing (hours)

P1

8

6

P2

3

2

P3

3

4

P4

4

6

P5

5

7

P6

6

4

P7

2

1

A
31
B
33
C
30
D
32
2
GATE ME 2017 Set 1
Numerical
+2
-0
Following data refers to the jobs $$(P, Q, R, S)$$ which have arrived at a machine for scheduling. The shortest possible average flow time is ___________ days. GATE ME 2017 Set 1 Industrial Engineering - Scheduling Question 6 English
Your input ____
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 8 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 7 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

A
$$0$$
B
$$2$$
C
$$6$$
D
$$8$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12