1
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Six jobs arrived in a sequence as given below: GATE ME 2009 Industrial Engineering - Scheduling Question 7 English

Average flow time (in days) for the above jobs using Shortest Processing Time rule is

A
$$20.83$$
B
$$23.16$$
C
$$125.00$$
D
$$139.00$$
2
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A set of $$5$$ jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. $$K$$ per day. GATE ME 2008 Industrial Engineering - Scheduling Question 8 English

A schedule that minimizes the total inventory cost is

A
$$T - S - Q - R - P$$
B
$$P - R - S - Q - T$$
C
$$T - R - S - Q - P$$
D
$$P - Q - R - S - T$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12