1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
The table gives details of an assembly line. GATE ME 2006 Industrial Engineering - Line Balancing Question 1 English

What is the line efficiency of the assembly line?

A
$$70\% $$
B
$$75\% $$
C
$$80\% $$
D
$$85\% $$
2
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce $$80$$ units during a regular $$8$$-hour shift. This operation consists of three activities as below . GATE ME 2004 Industrial Engineering - Line Balancing Question 2 English

For line balancing the number of work stations required for the activities $$M, E$$ and $$T$$ would respectively be

A
$$2, 3, 1$$
B
$$3, 2, 1$$
C
$$2, 4, 2$$
D
$$2, 1, 3$$
3
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
In an assembly line for assembling toys, five workers are assigned tasks which take times of $$10, 8, 6, 9$$ and $$10$$ minutes respectively. The balance delay for the line is
A
$$43.3\% $$
B
$$14.8\% $$
C
$$14.0\% $$
D
$$16.3\% $$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
CBSE
Class 12