1
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
In an assembly line for assembling toys, five workers are assigned tasks which take times of $$10, 8, 6, 9$$ and $$10$$ minutes respectively. The balance delay for the line is
Questions Asked from Line Balancing (Marks 2)
Number in Brackets after Paper Indicates No. of Questions