1
MCQ (Single Correct Answer)

GATE ME 2004

An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce $$80$$ units during a regular $$8$$-hour shift. This operation consists of three activities as below .

For line balancing the number of work stations required for the activities $$M, E$$ and $$T$$ would respectively be

A
$$2, 3, 1$$
B
$$3, 2, 1$$
C
$$2, 4, 2$$
D
$$2, 1, 3$$
2
MCQ (Single Correct Answer)

GATE ME 1996

In an assembly line for assembling toys, five workers are assigned tasks which take times of $$10, 8, 6, 9$$ and $$10$$ minutes respectively. The balance delay for the line is
A
$$43.3\% $$
B
$$14.8\% $$
C
$$14.0\% $$
D
$$16.3\% $$

Questions Asked from Line Balancing

On those following papers in Marks 2
Number in Brackets after Paper Name Indicates No of Questions
GATE ME 2006 (1)
keyboard_arrow_right
GATE ME 2004 (1)
keyboard_arrow_right
GATE ME 1996 (1)
keyboard_arrow_right

EXAM MAP

Graduate Aptitude Test in Engineering

GATE ECE GATE CSE GATE CE GATE EE GATE ME GATE PI GATE IN

Joint Entrance Examination

JEE Main JEE Advanced