1
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
The distribution of lead-time demand fro an item is as follows: GATE ME 2005 Industrial Engineering - Inventory Control Question 20 English

The reorder level is $$1.25$$ times the expected value of the lead-time demand. The service level is

A
$$25\% $$
B
$$50\% $$
C
$$75\% $$
D
$$100\% $$
2
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
There are two products P and Q with the following characteristics GATE ME 2004 Industrial Engineering - Inventory Control Question 22 English

The economic order quantity (EOQ) of products P and Q will be in the ratio.

A
$$1:1$$
B
$$1:2$$
C
$$1:4$$
D
$$1:8$$
3
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
A company has an annual demand of $$1000$$ units, ordering cost of Rs.$$100$$/order and carrying cost of Rs.$$100$$/unit –year. If the stock-out costs are estimated to be nearly Rs.$$400$$ each time the company runs out-of-stock, the safety stock justified by the carrying cost will be
A
$$4$$
B
$$20$$
C
$$40$$
D
$$100$$
4
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
Market demand for springs is $$8,00,000$$ per annum. A company purchases these springs in lots and sells them. The cost of making a purchase order is Rs.$$1,200.$$ The cost of storage of springs is Rs.$$120$$ per stored piece per annum. The economic order quantity is
A
$$400$$
B
$$2,828$$
C
$$4,000$$
D
$$8,000$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12