1
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
In a machine shop, pins of $$15mm$$ diameter are produced at a rate of $$1000$$ per month and the same is consumed at a rate of $$500$$ per month. The production and consumption continue simultaneously till the maximum inventory is reached. Then inventory is allowed to reduced to zero due to consumption. The lot size of production is $$1000.$$ If backlog is not allowed, the maximum inventory levels is
2
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
The maximum level of inventory of item is $$100$$ and it is achieved with infinite replenishment rate. The inventory becomes zero over one and half month due to consumption at a uniform rate. This cycle continuous throughout the year. Ordering cost is Rs.$$100$$ per order and inventory carrying cost is Rs. $$10$$ per item per month. Annual cost (in Rs. ) of the plan, neglecting material cost, is
3
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
A stockist wishes to optimize the number of perishable items he needs to stock in any month in his store. The demand distribution for this perishable item is:
The stockist pays Rs.$$70$$ for each item and he sells each at Rs.$$90.$$ if the stock is left unsold in any month, he can sell the item at Rs.$$50$$ each. There is no penalty for unfulfilled demand. To maximize the expected profit, the optimal stock level is:
4
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider the following data for an item.
Annual demand: $$2500$$ units per year Ordering cost: Rs.100 per order Inventory holding rate: $$25\% $$ of unit price. The optimum order quantity (in units) is:
Annual demand: $$2500$$ units per year Ordering cost: Rs.100 per order Inventory holding rate: $$25\% $$ of unit price. The optimum order quantity (in units) is:
Price quoted by a supplier
The optimum order quantity (in units) is
Questions Asked from Inventory Control (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME 2024 (1)
GATE ME 2016 Set 2 (1)
GATE ME 2016 Set 1 (1)
GATE ME 2015 Set 3 (1)
GATE ME 2014 Set 2 (1)
GATE ME 2014 Set 3 (1)
GATE ME 2010 (1)
GATE ME 2009 (1)
GATE ME 2007 (2)
GATE ME 2006 (2)
GATE ME 2005 (1)
GATE ME 2004 (2)
GATE ME 2003 (1)
GATE ME 1999 (1)
GATE ME 1991 (1)
GATE ME 1989 (1)
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude