1
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+2
-0.6
A manufacturer can produce $$12000$$ bearings per day. The manufacturer received an order of $$8000$$ bearings per day from a customer. The cost of holding a bearing in stock is Rs. $$0.20$$ per month. Setup cost per production run in Rs.$$500.$$ Assuming $$300$$ working days in a year, the frequency of production run should be
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Annual demand for window frames is $$10000.$$ Each frame costs Rs. $$200$$ and ordering cost is Rs. $$300$$ per order. Inventory holding cost is Rs. $$40$$ per frame per year. The supplier is willing to offer $$2\% $$ discount if the order quantity is $$1000$$ or more, and $$4\% $$ if order quantity is $$2000$$ or more. If the total cost is to be minimized, the retailer should
3
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
A company uses $$2555$$ units of an item annually. Delivery lead time is $$8$$ days. The recorder point (in number of units) to achieve optimum inventory is
4
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
In a machine shop, pins of $$15mm$$ diameter are produced at a rate of $$1000$$ per month and the same is consumed at a rate of $$500$$ per month. The production and consumption continue simultaneously till the maximum inventory is reached. Then inventory is allowed to reduced to zero due to consumption. The lot size of production is $$1000.$$ If backlog is not allowed, the maximum inventory levels is
Questions Asked from Inventory Control (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME 2024 (1)
GATE ME 2016 Set 2 (1)
GATE ME 2016 Set 1 (1)
GATE ME 2015 Set 3 (1)
GATE ME 2014 Set 2 (1)
GATE ME 2014 Set 3 (1)
GATE ME 2010 (1)
GATE ME 2009 (1)
GATE ME 2007 (2)
GATE ME 2006 (2)
GATE ME 2005 (1)
GATE ME 2004 (2)
GATE ME 2003 (1)
GATE ME 1999 (1)
GATE ME 1991 (1)
GATE ME 1989 (1)
GATE ME Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Turbo Machinery
Heat Transfer
Thermodynamics
Production Engineering
Industrial Engineering
General Aptitude