1
GATE ME 2016 Set 3
MCQ (Single Correct Answer)
+2
-0.6
The demand for a two-wheeler was $$900$$ units and $$1030$$ units in April $$2015$$ and May $$2015,$$ respectively. The forecast for the month of April $$2015$$ was $$850$$ units. Considering a smoothing constant of $$0.6,$$ the forecast for the month of June $$2015$$ is
2
GATE ME 2015 Set 1
Numerical
+2
-0
For a canteen, the actual demand for disposable cups was $$500$$ units in January and $$600$$ units in February. The forecast for the month of January was $$400$$ units. The forecast for the month of March considering smoothing coefficient as $$0.75$$ is_______________
Your input ____
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The demand and forecast for February are $$12000$$ and $$10275,$$ respectively. Using single exponential smoothening method (smoothening coefficient $$= 0.25$$), forecast for the month of March is
4
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A moving average system is used for forecasting weekly demand. $${F_1}\left( t \right)$$ and $${F_2}\left( t \right)$$ are sequences of forecasts with parameters $${m_1}$$ and $${m_2}$$, respectively, where $${m_1}$$ and $${m_2}\left( {{m_1} > {m_2}} \right)$$ denote the numbers of weeks over which the moving averages are taken. The actual demand shows a step increase from $${d_1}$$ to $${d_2}$$ at a certain time. Subsequently,
Questions Asked from Forecasting (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude