1
GATE ME 2025
MCQ (Single Correct Answer)
+2
-0.67
Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation, respectively, are
$$ \begin{array}{|c|c|c|c|c|c|c|c|c|c|c|} \hline \text { Period } & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & 9 & 10 \\ \hline \text { Actual demand } & 425 & 415 & 420 & 430 & 427 & 418 & 422 & 416 & 426 & 421 \\ \hline \text { Forecast } & 427 & 422 & 416 & 422 & 423 & 420 & 419 & 418 & 430 & 415 \\ \hline \end{array} $$
2
GATE ME 2016 Set 3
MCQ (Single Correct Answer)
+2
-0.6
The demand for a two-wheeler was $$900$$ units and $$1030$$ units in April $$2015$$ and May $$2015,$$ respectively. The forecast for the month of April $$2015$$ was $$850$$ units. Considering a smoothing constant of $$0.6,$$ the forecast for the month of June $$2015$$ is
3
GATE ME 2015 Set 1
Numerical
+2
-0
For a canteen, the actual demand for disposable cups was $$500$$ units in January and $$600$$ units in February. The forecast for the month of January was $$400$$ units. The forecast for the month of March considering smoothing coefficient as $$0.75$$ is_______________
Your input ____
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The demand and forecast for February are $$12000$$ and $$10275,$$ respectively. Using single exponential smoothening method (smoothening coefficient $$= 0.25$$), forecast for the month of March is
GATE ME Subjects
Browse all chapters by subject
Production Engineering
General Aptitude
Fluid Mechanics
Heat Transfer
Thermodynamics
Engineering Mechanics
Machine Design
Industrial Engineering
Strength of Materials
Engineering Mathematics
Theory of Machines
Turbo Machinery