1
GATE ME 1997
MCQ (Single Correct Answer)
+2
-0.6
In a forecasting model, at the end of period $$13,$$ the forecasted value for period $$14$$ is $$75.$$ Actual value in the periods $$14$$ to $$16$$ are constant at $$100$$. if the assumed simple exponential smoothing parameter is $$0.5,$$ then the $$MSE$$ at the end of period $$16$$ is
2
GATE ME 1989
MCQ (Single Correct Answer)
+2
-0.6
Which of the following is a technique for forecasting?