1
GATE ME 1998
MCQ (Single Correct Answer)
+1
-0.3
In inventory planning, extra inventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:
A
Lot – for – lot production
B
Economic Order Quantity $$(EOQ)$$ lot size
C
Period Order Quantity $$(POQ)$$ lot size
D
Part Period total cost balancing
2
GATE ME 1998
MCQ (Single Correct Answer)
+1
-0.3
One of the following statements about $$PRS$$ (Periodic Reordering System) is not true. Identify.
A
$$PRS$$ requires continuous monitoring of inventory levels
B
$$PRS$$ is useful in control of perishable items
C
$$PRS$$ provides basis for adjustments to account for variations in demand
D
In $$PRS,$$ inventory holding costs are higher than in Fixed Recorder Quantity System
3
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
Setup costs do not include
A
Labour cost of setting up machines
B
Ordering cost of raw material
C
Maintenance cost of the machines
D
Cost of processing the work piece
4
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
If the demand for an item is doubled and the ordering cost halved, the economic order quantity
A
remains unchanged
B
increases by a factor of $$\sqrt 2 $$
C
is doubled
D
is halved
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12