1
GATE ME 2011
MCQ (Single Correct Answer)
+1
-0.3
The word Kanban is most appropriately associated with
A
economic order quantity
B
just-in-time production
C
capacity planning
D
product design
2
GATE ME 2002
MCQ (Single Correct Answer)
+1
-0.3
An item can be purchased for Rs.$$100.$$ The ordering cost is Rs.$$200$$ and the inventory carrying cost is $$10\% $$ of the item cost per annum. If the annual demand is 4000 units, the economic order quantity (in units) is
A
$$50$$
B
$$100$$
C
$$200$$
D
$$400$$
3
GATE ME 1998
MCQ (Single Correct Answer)
+1
-0.3
In inventory planning, extra inventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:
A
Lot – for – lot production
B
Economic Order Quantity $$(EOQ)$$ lot size
C
Period Order Quantity $$(POQ)$$ lot size
D
Part Period total cost balancing
4
GATE ME 1998
MCQ (Single Correct Answer)
+1
-0.3
One of the following statements about $$PRS$$ (Periodic Reordering System) is not true. Identify.
A
$$PRS$$ requires continuous monitoring of inventory levels
B
$$PRS$$ is useful in control of perishable items
C
$$PRS$$ provides basis for adjustments to account for variations in demand
D
In $$PRS,$$ inventory holding costs are higher than in Fixed Recorder Quantity System
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12