1
GATE ME 2012
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following is NOT a decision taken during the aggregate production planning stage?
A
Scheduling of machines
B
Amount of labour to be committed
C
Rate at which production should happen
D
Inventory to be carried forward
2
GATE ME 2001
MCQ (More than One Correct Answer)
+1
-0.3
Production flow analysis $$(PFA)$$ is a method of identifying part families that uses data from
A
engineering drawings
B
production schedule
C
bill of materials
D
route sheets
3
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is
A
$$4$$
B
$$8$$
C
$$16$$
D
$$24$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12