1
GATE ME 2014 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A component can be produced by any of the four processes $${\rm I},$$ $${\rm II},$$ $${\rm III},$$ and $${\rm IV}$$. The fixed cost and the variable cost for each of the processes are listed below. The most economical process for producing a batch of $$100$$ pieces is GATE ME 2014 Set 2 Industrial Engineering - Production Planning and Control Question 5 English
A
$${\rm I}$$
B
$${\rm I}$$$${\rm I}$$
C
$${\rm I}$$$${\rm I}$$$${\rm I}$$
D
$${\rm IV}$$
2
GATE ME 2012
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following is NOT a decision taken during the aggregate production planning stage?
A
Scheduling of machines
B
Amount of labour to be committed
C
Rate at which production should happen
D
Inventory to be carried forward
3
GATE ME 2001
MCQ (More than One Correct Answer)
+1
-0.3
Production flow analysis $$(PFA)$$ is a method of identifying part families that uses data from
A
engineering drawings
B
production schedule
C
bill of materials
D
route sheets
4
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is
A
$$4$$
B
$$8$$
C
$$16$$
D
$$24$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
CBSE
Class 12