1
GATE ME 2014 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A component can be produced by any of the four processes $${\rm I},$$ $${\rm II},$$ $${\rm III},$$ and $${\rm IV}$$. The fixed cost and the variable cost for each of the processes are listed below. The most economical process for producing a batch of $$100$$ pieces is GATE ME 2014 Set 2 Industrial Engineering - Production Planning and Control Question 5 English
A
$${\rm I}$$
B
$${\rm I}$$$${\rm I}$$
C
$${\rm I}$$$${\rm I}$$$${\rm I}$$
D
$${\rm IV}$$
2
GATE ME 2012
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following is NOT a decision taken during the aggregate production planning stage?
A
Scheduling of machines
B
Amount of labour to be committed
C
Rate at which production should happen
D
Inventory to be carried forward
3
GATE ME 2001
MCQ (More than One Correct Answer)
+1
-0.3
Production flow analysis $$(PFA)$$ is a method of identifying part families that uses data from
A
engineering drawings
B
production schedule
C
bill of materials
D
route sheets
4
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is
A
$$4$$
B
$$8$$
C
$$16$$
D
$$24$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12