1
GATE ME 1990
Subjective
+5
-0
Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below GATE ME 1990 Industrial Engineering - Scheduling Question 5 English

Considering mean lateness and mean flow time, evaluate the shortest-time rule and least-slack rule and recommend the desirable rule.

GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12