1
GATE ME 1990
Subjective
+5
-0
Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below GATE ME 1990 Industrial Engineering - Scheduling Question 3 English

Considering mean lateness and mean flow time, evaluate the shortest-time rule and least-slack rule and recommend the desirable rule.