A job shop incurs a cost of Rs.$$60$$/- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with the following data:
![GATE ME 1996 Industrial Engineering - Scheduling Question 4 English](https://gateclass.cdn.examgoal.net/lDl7SY6bFahBckXuS/7mB1VbMq7hcFnngRUeGv5iHEM68SO/z0RMgtwyhOFb2AGUEwV6Bk/uploadfile.jpg)
Which schedule will minimize the total cost?
What is the minimum total cost?
Which jobs (if any) fail to meet their due dates?
2
GATE ME 1990
Subjective
+5
-0
Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below
![GATE ME 1990 Industrial Engineering - Scheduling Question 5 English](https://imagex.cdn.examgoal.net/p4UYAiMsu0WOwggyj/gjhYvE1jsWoqYgDXKdh1yTrGqrtVx/SqoBFfcrjSc1G6KukzqCQP/image.png)
Considering mean lateness and mean flow time, evaluate the shortest-time rule and least-slack rule and recommend the desirable rule.
Questions Asked from Scheduling (Marks 5)
Number in Brackets after Paper Indicates No. of Questions
GATE ME Subjects
Engineering Mechanics
Machine Design
Strength of Materials
Heat Transfer
Production Engineering
Industrial Engineering
Turbo Machinery
Theory of Machines
Engineering Mathematics
Fluid Mechanics
Thermodynamics
General Aptitude