1
GATE ME 2001
MCQ (Single Correct Answer)
+2
-0.6
resistance spot welding is performed on two plates of $$1.5$$ $$mm$$ thickness with $$6$$ $$mm$$ diameter electrode, using $$15000$$ $$A$$ current for a time duration of $$0.25sec$$. assuming the interface resistance to be $$0.0001\Omega ,$$ the heat generated to form the weld is
A
$$5625$$ $$W$$-$$sec$$
B
$$8437$$ $$W$$-$$sec$$
C
$$22500$$ $$W$$-$$sec$$
D
$$33750$$ $$W$$-$$sec$$
2
GATE ME 1996
Subjective
+2
-0
GATE ME 1996 Production Engineering - Welding Process Question 28 English
3
GATE ME 1991
Subjective
+2
-0
GATE ME 1991 Production Engineering - Welding Process Question 29 English