1
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
In arc welding of a butt joint, the welding speed is to be selected such that highest cooling rate is achieved. Melting efficiency and heat transfer efficiency are $$0.5$$ and $$0.7$$, respectively. The area of the weld cross section is $$5$$ $$m{m^2}$$ and the unit energy required to melt the metal is $$10\,\,J/m{m^3},$$ if the welding power is $$2$$ $$kW,$$ the welding speed in $$mm/s$$ is closet to
A
$$4$$
B
$$14$$
C
$$24$$
D
$$34$$
2
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
Two metallic sheets, each of $$2.0$$ $$mm$$ thickness are welded in lap joint configuration by resistance spot welding at a welding current of $$10$$ $$KA$$ and welding time of $$10$$ milliseconds. A spherical fusion zone extending up to the full thickness of each sheet is formed. The properties of the metallic sheets are given below:
Ambient temp $$=293$$ $$K$$
Melting point temp $$=1793$$ $$K$$
Density $$ = 7000kg/{m^3}$$
Latent heat of fusion $$=300$$ $$kJ/kg$$
Specific heat $$=800$$ $$J/kgK$$

Assume:
(i) Contact resistance along sheet - sheet interface is $$500$$ micro-ohm and along
$$\,\,\,\,\,\,$$electrode-sheet interface is zero.:
(ii) No conductive heat loss through the bulk sheet material; and
(iii) The complete weld fusion zone is at the melting temperature, the melting
$$\,\,\,\,\,\,\,\,\,$$efficiency (in %) of the process is .........

A
$$50.37$$
B
$$60.37$$
C
$$70.37$$
D
$$80.37$$
3
GATE ME 2007
MCQ (Single Correct Answer)
+2
-0.6
A $$DC$$ welding machine with a linear power source characteristic provides open circuit voltage of $$80V$$ and short circuit current of $$800A,$$ during welding with the machine , the measured are current is $$500A$$ corresponding to an arc length of $$5.0$$ $$mm$$ and the measured are current $$460A$$ corresponding to an arc length of $$7.0$$ $$mm.$$ The linear voltage $$(E)$$ & arc length $$(L)$$ characteristic of the welding arc can be given as (where $$E$$ is in Volts and $$L$$ is in $$mm$$)
A
$$E=20+2L$$
B
$$E=20+8L$$
C
$$E=80+2L$$
D
$$E=80+8L$$
4
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
In arc welding process, the voltage and current are $$25V$$ and $$300A$$ respectively. The arc heat transfer efficiency is $$0.85$$ and welding speed is $$8$$ $$mm/sec$$. The net heat input (in $$J/mm$$) is
A
$$64$$
B
$$797$$
C
$$1103$$
D
$$79700$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12