1
GATE ME 2022 Set 1
Numerical
+2
-0

Two mild steel plates of similar thickness, in butt-joint configuration, are welded by gas tungsten arc welding process using the following welding parameters.

$$ \begin{array}{|l|l|} \hline \text { Welding voltage } & 20 \mathrm{~V} \\ \hline \text { Welding current } & 150 \mathrm{~A} \\ \hline \text { Welding speed } & 5 \mathrm{~mm} / \mathrm{s} \\ \hline \end{array} $$

A filler wire of the same mild steel material having 3 mm diameter is used in this welding process. The filler wire feed rate is selected such that the final weld bead is composed of 60% volume of filler and 40% volume of plate material. The heat required to melt the mild steel material is 10 J/mm3. The heat transfer factor is 0.7 and melting factor is 0.6. The feed rate of the filler wire is __________ mm/s (round off to one decimal place).

Your input ____
2
GATE ME 2016 Set 2
Numerical
+2
-0
The voltage - length characteristic of a direct current arc in an arc welding process is $$V=$$ $$(100+40l),$$ where $$l$$ is the length of the arc in $$mm$$ and $$V$$ is arc voltage in volts. During a welding operation, the arc length varies between $$1$$ and $$2$$ $$mm$$ and the welding current is the range $$200$$-$$250A$$. Assuming a linear power source, the short circuit current is _____________$$A.$$
Your input ____
3
GATE ME 2016 Set 3
Numerical
+2
-0
Spot welding of two steel sheets each $$2$$ $$mm$$ thick carried out successfully by passing $$4$$ $$kA$$ of current for $$0.2$$ seconds through the electrodes. The resulting weld nugget formed between the sheets is $$5$$ $$mm$$ in diameter. Assuming cylindrical shape for the nugget, the thickness of the nugget is ______________$$mm.$$ GATE ME 2016 Set 3 Production Engineering - Welding Process Question 19 English
Your input ____
4
GATE ME 2015 Set 2
MCQ (Single Correct Answer)
+2
-0.6
During a $$TIG$$ welding process, the arc current and arc voltage were $$50$$ $$A$$ and $$60$$ $$V,$$ respectively, when the welding speed was $$150$$ $$mm/min.$$ In another process, the $$TIG$$ welding is carried out at a welding speed of $$120mm/min$$ at the same arc welding voltage and heat input to the material so that weld quality remains the same. The welding current (in $$A$$) for this process is
A
$$40.00$$
B
$$44.72$$
C
$$55.90$$
D
$$62.25$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12