1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
In arc welding process, the voltage and current are $$25V$$ and $$300A$$ respectively. The arc heat transfer efficiency is $$0.85$$ and welding speed is $$8$$ $$mm/sec$$. The net heat input (in $$J/mm$$) is
A
$$64$$
B
$$797$$
C
$$1103$$
D
$$79700$$
2
GATE ME 2005
MCQ (Single Correct Answer)
+2
-0.6
Spot welding of two $$1$$ $$mm$$ thick sheets of steel (density $$ = 8000kg/{m^3}$$ ) is carried out successfully by passing a certain amount of current for $$0.1$$ second through the electrodes. The resultant weld nugget formed is $$5$$ $$mm$$ in diameter and $$1.5$$ $$mm$$ thick. If the latent heat of fusion of steel is $$1400$$ $$kJ/kg$$ and the effective resistance in the welding operation is $$200\mu \Omega ,$$ the current passing through the electrodes is approximately
A
$$1480$$ $$A$$
B
$$3300$$ $$A$$
C
$$4060$$ $$A$$
D
$$9400$$ $$A$$
3
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
Two 1 mm thick steel sheets are to be spot welded at a current of $$5000$$ $$A.$$ Assuming effective resistance to be $$200$$ micro-ohms and current flow time of $$0.2$$ second, heat generated during the process will be
A
$$0.2$$ Joule
B
$$1$$ Joule
C
$$5$$ Joule
D
$$1000$$ Joules
4
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
Match the following GATE ME 2003 Production Engineering - Welding Process Question 33 English
A
$$P - 2,\,\,Q - 5,\,\,R - 1,\,\,S - 3$$
B
$$P - 6,\,\,Q - 3,\,\,R - 4,\,\,S - 4$$
C
$$P - 4,\,\,Q - 1,\,\,R - 6,\,\,S - 2$$
D
$$P - 5,\,\,Q - 4,\,\,R - 2,\,\,S - 6$$
GATE ME Subjects
Turbo Machinery
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12